For the past week, I've been working on the guest house floor, and I finished the last room today (except for the final row, which has to be cut to size on a table saw, which I don't have).
Tuesday, December 31, 2013
Thursday, December 19, 2013
Roofing Work Continues
The roof on the master suite is almost done, and progress is being made on the main building.
Looking towards the back of the house and master suite (with the shed in the background) |
The shed roof framing is done, and the siding is up |
Breezeway roof framing |
Tuesday, December 10, 2013
More Roofing
Work on the main building roof has started.
The framing of the breezeway between the main building and the master suite is done.
The trenching is done, the water lines are in, and the trench was filled with sand.
While we had the excavator, we also dug a trench for a future downspout discharge on the back of the master suite. The water will be released in the forest about 15 feet behind the house.
While working in the forest, I discovered a small tree fern.
It could be a Hawaiian tree fern, known as a Hapu'u, which is endemic to Hawaii, or an Australian tree fern, which is an invasive. The tree ferns can grow as tall as 25 feet.
View from the office |
The trenching is done, the water lines are in, and the trench was filled with sand.
While we had the excavator, we also dug a trench for a future downspout discharge on the back of the master suite. The water will be released in the forest about 15 feet behind the house.
While working in the forest, I discovered a small tree fern.
It could be a Hawaiian tree fern, known as a Hapu'u, which is endemic to Hawaii, or an Australian tree fern, which is an invasive. The tree ferns can grow as tall as 25 feet.
Wednesday, December 4, 2013
Shed Framing and Trenching
The framing of the shed is done.
When completed, the water heater/tank, water pump, and filters will go in the shed, so we need to run a supply pipe from the water tank to the shed, and another pipe from the shed to the guest house. The ground is mostly solid lava or a much of lava chunks and gravel, and it's difficult to dig even with an excavator.
These are the pieces from the leftover concrete, broken up by the excavator. We can use them as pavers.
When completed, the water heater/tank, water pump, and filters will go in the shed, so we need to run a supply pipe from the water tank to the shed, and another pipe from the shed to the guest house. The ground is mostly solid lava or a much of lava chunks and gravel, and it's difficult to dig even with an excavator.
Digging the trench for the water lines. |
Tuesday, December 3, 2013
Gravel for Driveway
We got a truckload of gravel (something like 20 cubic yards) for the driveway.
Mitch spreading out and packing down the gravel |
Monday, November 18, 2013
Main Building Siding
The first siding on the main building is up.
The siding on the front of the master suite and the front door were also installed.
The siding on the front of the master suite and the front door were also installed.
Site of future master suite side wall and side door |
Friday, November 15, 2013
First Siding Up
The first of the siding panels are up. We've been painting the grooves first, because it is much easier to paint before they are put up (it has to be done by brush, since a roller can't gt into the grooves), and the tops and bottoms (for the sake of neatness).
The forms were taken off the concrete slabs.
Far side of the master suite |
Back of the master suite |
Other side of the master suite |
Shed |
Landing for kitchen door |
Landing for back lanai (the shed pad is in the background) |
Wednesday, November 13, 2013
Concrete landings poured
We poured the concrete for the exterior stair landings today.
Form for the main house front landing |
Kitchen door landing form |
In front of the main building |
In front of the master suite |
Next to the kitchen |
Landing for the staircase from (what will become) the back lanai |
Shed for the water heater, water pump filtration system, etc. The thicker part will be the enclosed shed, and the thinner part will be a "covered porch" space. |
Tuesday, November 12, 2013
More windows
More of the windows are in.
The roofing work is also progressing.
Next to the front door and laundry room |
Front door |
Master suite closet (left) and bathroom (right) |
Monday, November 11, 2013
First banana harvest
The bananas have been growing for a while (http://big-island-living.blogspot.com/2013/08/post-pour-concrete-work-first-bananas.html), and the finally stated to ripen, so we cut them off the trees. We got two pretty big bunches. These are apple bananas, which are a bit smaller than supermarket (Cavendish) bananas, but they're sweeter and have a nice texture.
Wednesday, November 6, 2013
Breezeway framing done & roof started
The framing of the breezeway connecting the main building to the master suite is done. For the breezeway, trusses were not used, and each rafter is put in individually.
The roofing on the master suite has also been started.
The purlins on the office are done, and it's ready for roofing too.
Temporary treads were put on the stairs, making it a lot easier to get up and down.
The roofing on the master suite has also been started.
Mitch and Lucky working on the roof |
Temporary treads were put on the stairs, making it a lot easier to get up and down.
Landing at the top |
Subscribe to:
Posts (Atom)