Monday, November 24, 2014

Breezeway Ceiling

We finished installing the board over the front lanai and got started on the first breezeway.
Looking into the laundry room from the breezeway


Friday, November 21, 2014

Lanai Ceiling Installation and Railings

We started installing the ceiling over the covered lanais. The ceilings over both front lanais (in front of the main house and the master suite) and both breezeways need to be sealed (since they would otherwise be open to the attic spaces).
These are the same 16-foot long, 5-inch wide tongue-and-groove boards we used for the office ceiling. I've spent the last several weeks staining and finishing them -- there are about 270 boards total.
Lanai in front of the main house 
View from the other side
Some work has also been done on installing the railings on the lanais.
Master bedroom side lanai looking towards the back of the house

Looking towards the front

In front of the master bedroom